Electrical Trench Backfilled

Considerable progress was made the past week completing the electrical conduit connections between rooms and backfilling the trench. The team poured several more footings in various zones of the jobsite. They also prepared the final footings to ready the site for grading and an upcoming slab-on-grade pour. Shoring is being used to stabilize the area where sanitary line is being installed. Additionally, the fire riser was installed.